This Shower Renovation Hillside involved the refurbishment of three shower areas, including a complete renovation of the main shower featured in this project. The work included shower preparation, new Aquacheck plaster sheets, waterproofing, a custom shower niche, client-supplied tiling, new grout and silicone, and a new chrome semi-frameless shower screen.

Before

Hillside bathroom1 shower renovation before
Hillside ensuite_shower renovation before
Hillside shower renovation before

During the Project

Hillside bathroom shower wall during renovation
Hillside-bathroom2-shower-during1-renovation
Hillside ensuite shower during removal renovation

Finished Project

Hillside bathroom shower screen and niche after renovation
Hillside bathroom shower screen and niche after renovation

PROJECT OVERVIEW

Hillside Bathroom Renovation – Shower Area

This Hillside bathroom renovation involved removing the existing shower screens, old wall tiles and plaster from the ensuite and two bathroom shower areas to prepare them for renovation.

The existing shower bases in the ensuite and one of the bathrooms were removed and replaced by a plumber.

Sergio Tiling installed new Aquacheck plaster sheets, prepared and waterproofed the shower areas, and created a practical shower niche for storage. The client supplied the tiles, which were professionally installed and finished with grout and silicone.

A new chrome semi-frameless shower screen was organised and installed to complete the renovated shower area.

The third shower was also renovated as part of the project, although its shower base was not replaced.

All renovation rubbish and removed materials were cleared from the site, leaving the renovated areas clean and ready to use.

MATERIALS USED

 

  • Aquacheck plaster sheets.
  • Waterproofing system for shower areas.
  • Client-supplied wall and floor tiles.
  • Grout and bathroom-grade silicone.
  • Chrome semi-frameless shower screen.
  • Two new shower bases supplied by client and installed by a plumber.

PROBLEM SOLVED

The existing showers areas needed to be stripped back and properly prepared before the new finishes could be installed.

Old tiles and plaster were removed, allowing the walls to be rebuilt with suitable Acquacheck plaster sheets and prepared for waterproofing.

The ensuite and bathroom shower bases were also removed and replaced by a plumber with two new shower screens.

The existing shower areas needed to be stripped back and properly prepared before the new finishes could be installed.

Old tiles and plaster were removed, allowing the walls to be rebuilt with suitable Aquacheck plaster sheets and prepared for waterproofing.

The shower bases in the ensuite and one bathroom were removed and replaced by a plumber with two new shower bases.

The shower areas were then waterproofed, and a practical shower niche was created to provide additional storage.

The renovated areas were finished with new tiles, grout and silicone, along with a chrome semi-frameless shower screen, creating a clean and functional result.

HILLSIDE PROJECT FAQ

Frequently asked questions

What areas of the bathroom were renovated?

The project included 3 separate showers in 2 Bathrooms and the Ensuite shower areas.

Were the existing shower bases replaced?

The existing shower base were replaced in the ensuite and the main bathroom only. The third shower did not required a shower base replacement.

Did Sergio Tiling supplied the tiles?

No. All the tiles for the project were supplied by the client.

Was the waterproofing included?

Yes. The shower areas were prepared and waterproofed before the new tiles were installed.

Was a shower niche installed?

Yes. A practical shower niche was created for all 3 showers as part of the renovation.

Did you installed the shower screens?

No, a professional was organised to install the 3 new chrome semi-frameless  shower screens.

What preparation was required before tiling?

The existing shower screen, old tiles and plaster were removed carefully not to cause any extra damage. New Acquacheck plaster sheets were installed and the shower areas were prepared and waterproofed before tiling.

Do you remove the renovation rubbish?

Yes. Removed all excess materials and renovation rubbish were cleared from the site as part of the project.